Problem:   Electrical Systems Testing
Cause:     Data Center Commissioning
Affects:   All Systems
Started:   06/23/2009 03:00 AM
Resolved:  06/23/2009 06:00 AM

Notes:

Case Construction Administration will be conducting a full load test of the KSL and Crawford Data Center Electrical Systems and Generators.

Successful completion of the test will result in no system downtime. However, there is a risk for a full power outage in either data center during this maintenance window.